- FRIDAY 03/11/2023
a. Mapping of the impacted areas continued.
b. Arrival of the Well killing barge.
c. Assessment of the impacted areas by clean up and recovery personnel from NEPL.
d. Deployment of booms to fortify the failed booms. - SATURDAY 04/11/2023
a. Positioning of the barge and connection of fittings.
b. Continuation and conclusion of mapping.
c. Estimated measurement of the flow rate per hour was carried out ( 40litres per hour). - SUNDAY 05/11/2023
a. Continuation of connection of fittings for well killing operation.